Project Description

Initial reported issues: Parkade leaks throughout, concrete failed, ramp failed.

Scope Of Work:

  • Chisel and crack chasing all leaks in all levels of the parkade, Kryton repair.
  • Kryton T1 & T2 application on all foundation walls.
  • Excavate front property to install French drain, re-slope terrain for optimum natural drainage. Dual line to feed dry-well and carry to NE corner of the property.
  • Replacement of existing eavestroughs and downspouts.
  • Remove and replace parkade access ramp, membrane replacement.
  • Restoration of existing Allan block walls, complete landscaping and irrigation install.
  • Sealing of walkway joints at exterior interfaces.
  • Repair of cracks in the concrete foundation wall.
  • Concrete surface patching in the parkade.
  • Installation of new traffic coating in the parkade.

Completion 2017 / $525K